SUBSTRUCTURE:
Sub-frames consist of a 12” box truss design composed of side panels which feature 1 ½” x 1 ½” x 3/16” angle for the top & bottom cords and 1 ½” x 1 ½” x 3/16” angle members for the diagonal web in the side panels.

Cross trusses are located every 4’ with a diagonal between each truss on the bottom of the section against the floatation. 3” x 3” x 3/16” angle corner members are used where sections are joined with grade 8 bolts. COMPONENTS are hot dipped galvanized.

We also build substructure with extra reinforcement for golf cart traffic and wave break systems.


CONSTRUCTION METHOD:
Finger are positioned between head pier sections creating a pre-engineered reinforced joint where members meet. This is much stronger than simply attaching each fingers to the head pier as many builders do. Each finger section and head pier section is fabricated as an individual member then hot-dip galvanized. We also utilize underwater bracing as required for additional support, especially for wider and longer slips often seen in marinas. Wind bracing is used as required in the engineering process.


 

 



FLOATATION:
Floatation is roto-molded polyethylene tubs filled with white expanded polystyrene. Size and spacing of floats is determined in the engineering process to achieve load specifications for the project.



DECKING CHOICE:

  • Treated lumber: 2”x6” cross decked and screwed to treated 2”x4” sills tech screwed to sub-frames.
  • Composite: Choice Dek and other popular brands, installed directly to subframe. Many dock manufacturers use treated lumber runners to simplify the installation of the composite material. We tech screw composite decking to frames at recommended intervals by the manufacturer, to increase the life of the deck.
  • Concrete tiles: available per customer specification. We have many choices of concrete, ranging from a plain concrete to an natural looking aggregrate, painted surfaces, and even a tile with a marble look and feel.

Samples of Concrete:






METAL CANOPY:
Our roofing system consists of vertical columns constructed of 2 ½” sq. tubing which are bolted to the sub-frame with cross trusses in the substructure between each pair at their base.

As an option, we can inset roofing columns with pockets inside the substructure.

Purlins are 2 1/2 or 3 ½” x 8” galvanized 14 ga. “Z” with a maximum spacing of 8’. Heavier columns and purlins are used as required for larger slips and docks.

Roofing consists of 26-ga. "R-Panel" attached to purlins with gasketed, self-tapping hex head roofing screws and the seams are fastened with stitching screws.

Many choices of roofing are available with a veriety of colors. Pitch, rib pattern, and gauge are determined to match your job's requirements.

Center yoke systems and gable roofs are available.

Wind bracing on superstructure is used as determined in the engineering process on a per job basis.

ANCHORING:
Anchoring typically consists of size D galvanized cast iron winches attached to our corner mounted winch towers.

Winches are spooled with 1/2" or 5/8" galvanized aircraft cables, which terminate at concrete sea anchors outboard and shore anchors on land.

On large slips (houseboat & cruiser) or larger dock applications, we pour 9,000 lb. anchors onsite

We also utilize spud poles and stand off systems where conditions are appropriate.


GANGWAY & BRIDGES:
Gangway's have handrails on both sides.

The Signature series features 3” square tubing handrails trussed with 1 ½” square tubing.

The Standard series features 2” x 3/16” angle handrails trussed with 1 ½” x 3/16” angle.

We also build free span bridges and other custom designs to fit your marina situation.

Floating Walkway:
We can build floating walkways for connecting docks in a variety of styles and sizes.

 

OPTIONS:
Vinyl edging, bumpers, cleats, electric, and trussed corner sections.